Gold Member Since 2013
Audited Supplier
Hebei Lvjoe Machinery Manufacturing Co., Ltd.

Gypsum Board Production Line, Cheap Gypsum Board Production Line, Cheap Gypsum Board Equipment manufacturer / supplier in China, offering Annual Output 4000000 M2 Plaster Wallboard Production Line, Gypsum Powder Production Line, Gypsum Board Production Line and so on.

(/ )

Supplier Homepage Product gypsum board production line Others gypsum board production line Annual Output 4000000 M2 Plaster Wallboard Production Line

Annual Output 4000000 M2 Plaster Wallboard Production Line

FOB Price: Get Latest Price
Min. Order: 1 Set
Production Capacity: 12 Sets/Year
Transport Package: Suitable for Transportation by Sea/Train
Payment Terms: L/C, T/T, Money Gram
Basic Info
  • Model NO.: LVPB-4MHO
  • Automatic Production Line: Assembly
  • Automation: Automation
  • Rhythm: Flow Production Line
  • Final Production: Medium Quality, Suitable for More People
  • Machines Area: 100 X 15m
  • Operating Plant: Tanzania, Ethiopia, Sudan etc.
  • Special Service: Help You to Operate or Train
  • Dryer: Indirect Heat (Hot Oil)
  • Trademark: LVJOE MACHINERY
  • Origin: Shijiazhuang, Hebei Province
  • Transmission Type: Rigid
  • Certification: ISO, CE, BV
  • Flexible Production: Intelligent Manufacturing
  • Production Scope: Product Line
  • Advantage: No Need Skilled Worker
  • Workers: 15 Per Shift
  • PLC: Siemens
  • Some Additives: We Can Supply
  • Fuel: Coal, Wooden, Diesel or Gas
  • Specification: CE, SGS, BV
  • HS Code: 8474809090
Product Description

Buyer's obligation

Here are listed some items in order to solve those problems that are either too difficult or not possible for the seller to accomplish, to ensure the project develop smoothly.

8.1 Data exchange
For the necessary technical data exchange, the buyer is to provide all the necessary information for the project, including land drawing with correct and clear dimension on it. All the data or original data would be proved by the seller in written form.
Water report 
Weather condition, temperature, temperature difference, humidity,;
Gypsum powder report;
Fuel and its data;
Test criteria and method;
 
8.2 Help to the seller
The buyer is to help the seller doing those formalities concerning invitation letter, visa application and delayed staying visa.
 
8.3 Support to buyer
The buyer is to source the entire necessary human requirement for construction work, machine installation, commissioning, trial production and continuous production later.
 
 
8.4 Project manager
The buyer is to assign its project manager and site manager.
 
 
8.5 Additional cost
The buyer is to pay the additional human resource cost when more than specified people are required or longer time than the schedule to stay on site because of the buyer's reason, at the following charging rate:
 
8.6 meals/accommodation/traffic/etc
The buyer should be responsible for the installation personnel of the seller's accommodation, three meals in a day, traffic, insurance and the safety.  
 
8.7 Direction
It is expected that the buyer would help the seller's stuff in the life, such as to get life necessities, hair cutting, trip direction, and etc.
 
8.8 Site interpreter
The buyer is to send 2 site interpreters for Chinese/Arabic translation, to ensure efficient communication and coordination for site construction work and machine installation.
 
8.9 Medical expense
The buyer is to pay the medical expense for the injury or illness of seller's stuff in any case when these people.
 
8.10 Working tools
The buyer is to provide the following site support for site construction work and machine installation:
Crane and forklift
scaffold;
 
some tools or small machines listed below:
DescriptionModel or SpecUnitQuantityRemark
Drilling machine
Set1
Sand wheel grinding machine
Set1
Power supply415Vset4
Knife switch60APcs

Copper wire cable
mAs the needMultiple strand,
 3-cores 
Welding machine
set5
Welding electrodeΦ3.2carton

Weld handle cable
m200
Welder electrical cable
pc8
Welder mask
pc8
Grinding wheel saw
set3
Bottled Oxygen gas 
bottle2Spare one included
Bottled Acetylene gas
bottle2Spare one included
Oxygen Hoses
m200
 
8.11  Large engineering machines
The buyer is to hire those engineering machines required in board line installation:
 
8.12 Raw materials and lubricant
The buyer is to supply the following material on its own expense for commissioning, trial production and acceptance machine running:
² All the lubricants for gear box and bearings;
² Detergent for machine and hand washing;
² Raw materials of required quality such as:
Gypsum
Modified starch;
Foam agent;
Glass fiber;
silicon
Paper 
Glue band for paper connection;
8.13 Civil work
The buyer should be responsible for the workshop, the ground and the basic facilities of the equipment.
 
8.14 Facility-pipe and cable
The water pipes, water feeding system, the natural gas feeding pipes should be provided by the buyer.
 
8.15 Power supply
For the electric supply system, it takes the distribution cabinet as the borderline. The equipments before the distribution cabinet should be provided by the buyer. The equipments after the distribution cabinet will be supplied by the seller.
 
8.16 Labor
During the in stallion, all the non technical workers and assistant workers should be provided buy the buyer.
 
Annual Output 4000000 M2 Plaster Wallboard Production Line





8.17 Power station
Transformer, high and low pressure measurement cabinet, kinetic tank and power electric cable will be by buyer.
 
8.18 Water and fire extinguish
Inside and outside the room, draining water and the fire prevention will be by buyer.
 
8.19 Production water
The buyer will provide water supply with a temperature below 35°C and flow quantity of 12 tons per hour, to provide the water to the mixer.
 
8.20 Foundation and platform
All work in connection with the setting up of the offered machinery, in particular the steel structure for the buildings, platforms, stairs and railings, masonry and concrete work shall be executed by buyer,Machine foundations are to be worked out by buyer, the drawings of which shall be sent to the buyer 3 months before installation work begin.
 
8.21 Control rooms
Three operating control rooms in the production line and their decoration including air condition facility shall be built by buyer and the seller shall provide the dimensions and other requirement of these rooms.
 
8.22 Power supply to cabinet
5 machine power supply of 3 phase 4 wire shall be connected separately by buyer to the 6 site electric cabinets described on the layout as EL-group 1, EL-group 2, EL-group 3, EL-group 4, and  EL-group 5, the requirement of which shall be sent to the buyer one month after the project come into effective;
 
8.23 Control and maintenance powder supply to cabinet
       
5 power supply of 3 phase 4 for control system to produce 220 AC shall be connected separately by buyer to the 6 site electric cabinets described on the layout as EL-group 1, EL-group 2, EL-group 3, EL-group 4, and EL-group 5, the requirement of which shall be sent to the buyer one month after the project come into effective;
       

Annual Output 4000000 M2 Plaster Wallboard Production Line




 

5 Project schedule

5.1 customer project information exchange
 
5.2 contract signing
 
5.3 initial designing
In this stage the following designing work would be done:
² Machine layout including facilities;
² Calculating result of all process, upon which further designing work would develop;
² Customer's audit, in which the buyer would further ask customer's opinion over that and then modify it in order to get a final proof from customer;
 
5.4 Sub contract signing and purchasing
² Sub contract with sub suppliers for production line machines and facility;
² Raw materials purchasing for machine building;
 
5.5 Machine building
² Parts machining;
² Machine assembling;
² Machine test running within factory;
 
5.6 Document delivery including
² Drawing of all the foundation works
² Those document that are necessary before installation work begins;
 
5.7 contracted machine delivery including:
² Customer pre acceptance inspection, to clarify the right machine of right quantity would be delivered; dividable delivery is possible and allowed;
² Machine packaging;
² Inland transportation in China;
² Sea shipment;
² Customer clearance or any formality that is required by Qatar local government;
² Inland transportation in Qatar;
² Cargo unloading and storage;
 
5.8 Production line installation
² Board line installation;
 
5.9 Training program execution
² Training for lab. Test of board plant;
² Machine understanding training;
² Machine operation training;
² Production training;
Production operation;
Production quality control;
² Training examination;
 
5.10 Commissioning including:
² Board line commissioning:
Single machine commissioning;
Whole line commissioning without materials;
Whole line commissioning with materials;
 
5.11  Trial production including:
Trial production will star only when all training program have been fully executed.
² Board line trial production;
 
5.12 Project acceptance including:
² Board plant acceptance;
 

6 Project human resource

6.1 Project manager
The buyer and the seller will assign a project manager each side, whose responsibility is supervising the whole project process, to make coordination to ensure the project developing smoothly as scheduled.
 
6.2 Site manager
The buyer and the seller will assign a project manager each side, whose responsibility is supervising the whole project process on site, to make coordination to ensure the project develop smoothly as scheduled.
 
6.3 Engineers, technicians and labor
 
Human requirement for board plant erection

installationcommissioning
The sellersupervisor11
mechanical66
electrical11
total88
The buyersupervisor31
mechanical24
Welder 5
8
electrical62
total3311
 

7 Spare parts with machine

Below is spare parts delivered together with machine of no additional charge:
 
Item Spare partNumber 
1One set of spare parts for mixer1 set
3Saw of marking device(electroplating diamond grain)4 pcs
4knife to cut the board1 pcs
5Regular bearings20 pcs
6Anti-grinding bearings20pcs
7Chain gear20pcs
8Chain 10 pcs
9Forming line rollers6 pcs
10Drying room rollers6 pcs
11Photo-electronic switch5 pcs
12AC contactor4 pcs
13Reducer2 sets
14Motor1set
15Catch6pcs
16Switch20set
17Fuse20pcs
18Indicator light30pcs
19Motor for paper alignment device1 sets
20Mixer spare parts1 set
21Mixer1 set
22Forming device1 set
23Spare parts for one and half year1 set
 
Annual Output 4000000 M2 Plaster Wallboard Production Line
Send your message to this supplier
Avatar
Ms. Lisa
sales manager
*From:
To: Ms. Lisa
*Message:

Enter between 20 to 4,000 characters.

This is not what you are looking for? Post a Sourcing Request Now